HSE Department PlanHealth · Safety · Environment — APB South
Print / PDF ← Command Center
Health · Safety · Environment · Stock Island

The yard that operates inside a sanctuary.

Every gallon of water around this property sits inside the Florida Keys National Marine Sanctuary. That is not a constraint to work around — it is the operating identity: the yard that documents everything, spills nothing, and charges every waste stream to the vessel that generated it.

WHY THIS DEPARTMENT EXISTSThe stakes, named

A boatyard in the Lower Keys answers to more agencies, in a more sensitive place, than almost any yard in America. HSE here is not a binder on a shelf — it is the license to operate, the shield in a lawsuit, the pass mark in every vendor and government audit, and a paying department in its own right.

Who is watchingWhat they watch
NOAA — Florida Keys National Marine SanctuaryThe water itself. Discharge prohibitions across the sanctuary; anything leaving this property into the water is a federal matter.
EPA / FDEP — stormwater & wasteIndustrial stormwater permitting for boatyards (the multi-sector general permit and its Florida equivalent), used-oil and hazardous-waste handling, petroleum storage.
OSHA — 29 CFR 1915 & 1910Shipyard employment standards: hot work, confined spaces (tanks and bilges), fall protection, cranes and rigging, respiratory protection for paint and blast.
US Coast GuardSpill notification (the National Response Center) and anything that makes a sheen on the water.
Monroe County / City of Key WestLand use, derelict vessel process, fire marshal, noise and nuisance.
Verification note. The regulatory names above are the correct families; the exact permits this property needs (stormwater NOI, petroleum storage registration, SPCC applicability by tank volume) must be confirmed by the environmental consultant during the site survey — thresholds turn on facts like aggregate oil storage that are unverified until the survey.
The flag to fly: Florida Clean Boatyard designation. The state's voluntary designation is the visible proof that the yard runs clean — it belongs on the website, the gate sign, and every investor and government submission. The whole plan below doubles as the application checklist.

DOCTRINEThree rules the whole yard runs on

ORGANIZATIONWho owns it

SeatResponsibility
HSE Manager
Yard Manager, dual-hat at opening
Owns this plan. Runs inspections, incident response, training records, waste-vendor contracts, and the permit calendar. The opening roster already assigns the yard manager the HSE hat — a dedicated HSE hire is a growth-trigger decision, not a day-one cost.
Corporate Safety Coordinator
APB North — Jerry Clark
The company's existing written programs, training matrix and OSHA logs live at APB North. This plan adapts that library to the yard — it does not rewrite it. Corporate audits the yard quarterly.
Every supervisorOwns the safety of their crew and their patch of ground. Signs the hot-work permits, runs the toolbox talks, stops any job that isn't safe to continue.
Every handStop-work authority, no exceptions. Anyone can halt any job over safety or an imminent discharge — and the halt is thanked, not punished.
Contractor compliance deskAlready built: the contractor portal's green/yellow/red risk tiers, carrier-issued certificates, and the authorization agreement. HSE sets the tier definitions; the portal enforces them.

THE WASTE STREAMSEvery stream, handled and billed

This is the heart of the department: each stream has a container, a home, a disposal path, and a price. The price column is live — these are real line types on the Marina Manager folio, priced off the rate card's Environmental & HSE section.

StreamHandling on the yardLeaves the yard viaBilled as
Used oilSealed transfer to the used-oil tank at the waste depot; no open pans left outLicensed used-oil transporter, manifestedHSE · Used oil disposal ($/gal)
Oily bilge waterPumped, never dumped; oil-water separation before disposalLicensed transporterHSE · Oily water pump-out ($/gal)
Antifreeze / coolantDedicated drum, never the storm drainRecyclerHSE · Antifreeze disposal ($/gal)
Solvents & paint wasteFlammables locker; hazardous-waste drum, dated when the first drop goes inHazardous-waste hauler, manifestedHSE · Solvent & paint waste ($/gal)
Filters, rags, absorbentsContaminated-solids drum at the depotHazardous or special waste per contentHSE · Filters & absorbents ($ each)
BatteriesPalletized, terminals protected, under coverBattery recyclerHSE · Battery disposal ($ each)
Spent zincs & anodesScrap binMetal recyclerHSE · Spent anodes ($ each)
Sewage / holding tanksPump-out at the dock or on the hard — the agreement already requires an empty tank before the slingsSanitary system via pump-out serviceHSE · Holding-tank pump-out ($ flat)
Bottom-wash waterWash pad with capture — interim berms and vacuum recovery on day one, closed-loop recycling pad as the capital buildFiltered solids to special wasteinside the pressure-wash rate
Paint dust & blast mediaFull containment: tenting, tarps, vacuum sanders — APB-only bottom work makes this enforceableContaminated solids streaminside the paint job
Every hazardous pickupCarries its paperwork — the manifest is what proves where the waste went, and it is retained for the recordHSE · Waste manifest ($ each)
Plus the blanket: environmental recovery on every line. The card already carries the comparison yard's own billing shape — a percentage on every line item, printed as its own column. The stream charges above are on top: the recovery fee pays for the yard's standing compliance; the stream charges pay for the vessel's own waste.

SPILLSThree tiers, one phone number

TierWhat it looks likeResponse
Tier 1
On the ground
Small spill on pavement or ground, contained on propertyNearest spill kit — pads, absorbent, drum the waste. Logged same day; billed to the vessel or contractor that caused it.
Tier 2
Sheen on the water
Any petroleum reaching the water, any sizeBoom it immediately, then the legal duty: National Response Center 1-800-424-8802 — a sheen on sanctuary water is reportable, and failing to call is the bigger offense. FDEP watch office follows.
Tier 3
Beyond the yard
More than the kits and crew can holdContracted spill-response company (OSRO) on retainer — the contract is a Phase-2 deliverable. Yard crew holds the perimeter until they arrive.

Billing: a spill caused by a vessel or its contractor bills the callout (HSE · Spill response), cleanup labor by the hour (HSE · Environmental cleanup), and disposal of everything recovered — the polluter pays, on the yard's paper, documented photo-first like everything else.

THE PROGRAM LIBRARYThe written programs, phased honestly

APB already holds written HSE programs, a training matrix and OSHA logs at the corporate library — the work here is adaptation to a yard, not authorship from zero.

ProgramWhy the yard needs itPhase
Hot work permit systemWelding and cutting near fuel, foam and paint — permit per job, fire watch, signed by the supervisorDay one
Hazard communication + SDS libraryEvery chemical on the yard, findable in one placeDay one
PPE assessmentBy task: eyes, hearing, respiratory, feet, high-vis on the lift apronDay one
Spill response plan (this page, operationalized)Kits staged, tiers drilled, the NRC number posted at the fuel point and the officeDay one
Crane & rigging / lift plansThe 85-ton lift is the yard's beating heart — daily inspection, annual certification, written lift plan for anything unusualDay one
Stormwater plan (SWPPP + permit NOI)The industrial stormwater permit for boatyards — drains mapped and marked, benchmarks monitored30–90
SPCC planRequired when aggregate oil storage crosses the federal threshold — evaluate against actual tankage at survey, then write it30–90
Confined space programTanks, bilges, chain lockers — shipyard confined-space rules, permits and attendants30–90
LOTO · fall protection · respiratory protectionAdapted from the corporate programs to yard equipment and paint work30–90
Hurricane & severe weather planJune–November reality: haul-out surge protocol, tie-down standards, crew stand-down, restart inspectionBefore Sep
Derelict & legal-hold vessel protocolThe property inherits non-payers and derelicts — a written chain (notice, lien, county derelict process) keeps the cleanup lawful30–90
Clean Boatyard designation packageThe application that proves all of the above to the stateSeason

TRAININGWho learns what, and when

CourseWhoCadence
Yard orientation — the three rules, spill kits, stop-work, gate & lift apron disciplineEvery hand, every contractor, before first day of workOnce + annual refresh
Toolbox talksEvery crewWeekly, 10 minutes, logged
Spill response drillAll yard staffQuarterly; one wet drill before storm season
Hot work / fire watchWelders, fitters, their watchesAnnual
Lift & machine operationNamed operators onlyCertification + annual review
ForkliftNamed operators3-year cert cycle
First aid / CPRAt least one per shift on the ground2-year cycle
OSHA 10 (shipyard) — hands · OSHA 30 — supervisorsPer roleOnce, tracked
HAZWOPER awarenessThe spill-response core teamInitial + annual refresher

The corporate training/cert matrix already tracks this format at APB North — the yard inherits the system, adds the yard-specific rows, and the Cert Hub pattern from the PM Console is the tracking tool.

RECORDS & METRICSWhat gets written down, and what it proves

THE CLOCKPhased like everything else — operating first, audit-ready by season

Phase 1 · Days 1–30

Safe to operate, clean from the first haul

Spill kits staged at the lift, the fuel point, and the waste depot. Drums and containers on the ground before the first job. Hot-work permits, orientation, PPE, and the lift inspection regime live. The HSE billing menu is on the rate card — every stream chargeable from the first customer. NRC number posted.

Phase 2 · Days 30–90

The paper catches up to the practice

Stormwater NOI filed and drains marked; SPCC evaluated against surveyed tankage and written if triggered; confined space, LOTO, fall protection and respiratory programs adapted from the corporate library; the spill-response contractor retained; the derelict-vessel protocol drafted with counsel — it is also the legal backbone of the property cleanup.

Phase 3 · September–October

Storm-ready, then season-ready

Hurricane plan drilled in the quiet months; the wet spill drill run; training matrix current; OSHA log clean. Clean Boatyard application submitted so the designation can fly when the fleet arrives.

Season

Audit-ready as a way of life

Any surveyor, insurer, prime contractor or agency can walk in unannounced and find the records current — because the records are the operating system, not a scramble before the visit.

APB South · HSE Department Plan · August 2026 — working draft.
Prepared for internal planning. Regulatory references are summaries of publicly known program families and must be confirmed with qualified counsel and a licensed environmental consultant against the surveyed facts of the property (tank volumes, drainage, permits of record) before being relied upon. The corporate written programs, training matrix and OSHA logs referenced are APB's existing library at Fort Lauderdale; this plan adapts them to the yard.